After nine years, and an eye-watering R1.82bn forked out by the government, the new Siloam Hospital in Thohoyandou, Limpopo, is still unfinished, reports Daily Investor.
The project – planned in three phases, to replace the dilapidated, ageing original hospital – was supposed to cost R250m and take three years, former president Jacob Zuma had promised in 2011.
That’s 15 years since his announcement, and a full nine years since phase one started.
The government’s updated expenditure on the facility was revealed by Health Minister Aaron Motsoaledi in response to a Parliamentary question from National Assembly member Faith Muthambi last week.
Incredibly, Motsoaledi said that the hospital “has remained on schedule to date, with no cost overruns”.
“The main hospital is complete, and the rehabilitation centre was scheduled for practical completion by 20 October – but a court order halting certain ancillary works, specifically the storm-water attenuation pond, could delay overall project completion.”
Despite saying the project “is on schedule”, he also said several clearance permits from various government departments and agencies have been outstanding “for some time”.
“DWS must issue a water use licence for the attenuation pond, and DFFE must issue an environmental authorisation for the storm-water attenuation pond.
“Additionally, the Department of Public Works has been unresponsive regarding demolition permits for dilapidated buildings at Siloam, which is affecting the contractor’s progress on the external ancillary works.”
Nevertheless, he added confidently, the hospital planned to be fully operational in February 2027.